Sunday, June 22, 2008

Truss' Part Duex



Another Saturday of fun, Jim Acer, Ryan Keller, and Dave Charon were all suckered in to coming out to the house and putting in 5 hours of work. We got off to a slow start since we had trouble deciding on the best way to get the first truss placed. Once we got going though it went really well. We set 10 trusses in all, and laid alot of the ground work for the big truss which will hold up the load bearing wall which will be removed.

Friday, June 20, 2008

Setting Truss'



The Truss' showed up this week, and at the last minute, I decided to have a crane come out and set the bundle on the walls in order to save a lot of time and effort when we frame the roof. I figured it would be nice to do this for my crew that is doing the roof. (especially since the crew is unpaid!!!!)

Sunday, June 15, 2008

Framing (First Half)




Framing finally started. Saturday June 14th, we had a large crew of about 8 guys come help raise the walls. Earl was the "boss man" for the day, and kept us working in the right direction. We raised the 27' wall first, then moved on to the 20' wall with the french doors, and finished the day with completing most of the other 20' wall which has two windows.


concrete pour




On Monday June 9th we had 16 yards of concrete poured into our pad. 8 inches thick in the middle, and 12 inches thick on the outer two feet. Paid a crew to come out and finish the concrete.


Post Tension


Post tension crew came up from phoenix on a saturday, we had to cut 7 existing cables, remove them and replace them with longer cables that will be continious through both slabs.